Construction Update November 2017

Posted: November 7, 2017 at 1:19 pm

Overall Works In Progress

  1. Peterson Hall, Fairfax Campus – June 2015 to December 2017
  2. Hazel Hall Library Renovation, Arlington Campus – August to November 2017
  3. Hylton Center Addition, Sci-Tech Campus – February to December 2018
  4. Robinson Hall and Harris Theater Renovations, Fairfax Campus – September 2018 to December 2022
  5. PPEA Discovery Hall Renovation, Sci-Tech Campus – May 2017 to February 2018
  6. Bull Run Hall Renovation, Sci-Tech Campus – August 2018 to September 2020

Peterson Hall

The new Health and Human Services academic building will be open for Spring 2018 semester classes. Offices are expected to open in January, 2018. The clinic, however, will not be open until a later date.

Potomac Science Center

The new Potomac Science Center is now open, and everyone has moved in. They are already doing cool research, which can be seen on their Facebook page: Potomac Environmental Research and Education Center

The Hub Renovation

Print Services is expected to move into The Hub mail room space in Spring 2018.

Arlington Campus

The Hazel Hall Library Renovation on the first and second floors began in August 2017 and is expected to be complete in November 2017.

Science and Technology Campus

The planned Hylton Center Addition has just been approved and renovations are expected to begin in February 2018.

Renovations for Bull Run Hall 3rd Floor Fitout have been approved and are currently in the planning process.

For more information on future plans for construction and renovations, visit the Facilities website page on Project Listings.

Write to University Information at building@gmu.edu

No Comments

Questions?

Do you have questions about construction? building@gmu.edu Then just ask!

What's the current traffic around Mason? Check out WTOP 103.5 FM or call 511 (free real-time traffic info through VDOT)

Mason Twitter News